Woodbury Councilmen Tom Burke and Bob Hunter recently joined Jerre Coleman with Fusco Engineering as he oversaw the soil boring test at the site of the John P. Burke Memorial Pool. Photos provided by Maria Hunter.

Residents can view the current drawings of the John P. Burke Memorial Pool at Town Hall located at 615 Route 32 in Highland Mills.

Work on the John P. Burke Memorial Pool is expected to begin on or about July 1.

It’s estimated that the $2,558,000 project will take 180 days to complete.
Construction on the John P. Burke Memorial Pool is expected to start on July 1, with a 180-day completion timeline.
The estimated cost is $2,558,000; bids were received for pool renovations only.